Issue Description
When a task in the workflow expired after a certain period, the Average Duration under the Activities does not correlate to the Task under Activity Duration on the workflow report.
Resolution
- Ensure you have K2 Five (5.2) installed.
- Download and install the K2 Five (5.2) May 2019 Cumulative Update from K2 Partner and Customer Portal.
- Download the K2 Five (5.2) May 2019 Cumulative Update FP1 from K2 Partner and Customer Portal.
- Install the K2 Five (5.2) May 2019 Cumulative Update FP1 to apply the fix.