If a system is tagged in a process, is the system stakeholder automatically added to the RACI matrix for that process or would they need to be added manually?

Best answer by Noala

Yes, our experience is that system owners are automatically added to the RACI by Promapp when a system is referenced (tagged) in a process.
They appear in the Informed section of the RACI as shown in this screenshot:

 

View original

3 replies

TraceyMcK
  • Jun 24, 2021 11:00 PM UTC

In my organisation the System owner and system are separate data points, so the system owner would need to be added.

Translate

Noala
Forum|alt.badge.img+8
  • Answer
  • Jun 25, 2021 2:22 AM UTC

Yes, our experience is that system owners are automatically added to the RACI by Promapp when a system is referenced (tagged) in a process.
They appear in the Informed section of the RACI as shown in this screenshot:

 

Translate

  • Author
  • Nintex Partner
  • Jun 25, 2021 1:00 PM UTC