Does ProMapp support the ability to create a process that has non sequential activities in it? Currently, if I create a process, even if activities are unassigned, it creates a linkage between them. The activities in the process I want to construct can be actioned in any order so I don't need the sequencing.

1 reply

aejones
  • December 22, 2020
you can select 'parallel with prev' or 'parallel with next' from the wheel icon of each activity