Hello,
I have a state machine with 4 stages after every stage I do have a change state to kick to the next stage. I have attached screen shots but if they are to small let me know I will try to send bigger ones. the State machine will go through all 4 stages and give me the end status under "in progress" in the workflow, but then it will kick off the first email from the first stage right after. I have added change state with end state machines and end workflow at the end of the 4th stage on all branches. Not sure what I am doing wrong here. In stage 1 I do have a parallel action to kick off 2 different assign flexi tasks but this is kicking off the 3 branch. So I have a set a condition then off the one condition is the parallel action.