Skip to main content
Nintex Community Menu Bar

Drawloop - Scheduled Report sent out on the wrong day after changing the day or time

  • March 26, 2021
  • 0 replies
  • 66 views

KB_Admin
Nintex Employee
Forum|alt.badge.img+8

Issue

When the day or time on a scheduled report is changed -  the report is sent out on the original day/time

 

Resolution

  • Deactivate the report
  • Change the date/time
  • Save
  • Activate the report
  • Additionally, this will need to be done to account for Daylight Savings times.