Does anyone know the possible values of K2.Activity.Status (this is one of the variables you can test in the Add Rule window).

For example, does a completed activity have a status of "Complete" or "Completed"?

This does not appear to be documented anywhere.

Thanks

Simon Ainsworth
The posible values can be found in the NameSpace SourceCode.KO.ActInstStatus

The posible values are:
Active
Completed
Empty
Expired
Waiting
Does anyone understand what the "waiting" status is for ?

My process instances show up in Service manager as active, but are not be assigned to the worklist ?

Locating these process instances in the workspace shows them as status "waiting" ??

Thanks,
Chris White.
Hi

'Waiting' indicates that the Activity has been reached but is not active yet. This is typically true when a start rule is configured and has not yet completed.

Emile
Hi Emile,

Thanks for replying.

I have no start rules configured. I think the reason they are "waiting" is something to do with active directory, but can't figure out a) what's causing it or b) how to solve it !!

It's as if K2.NET is trying to decide who to deliver the activity to and is having trouble communicating with AD.

Thanks,
Chris.

Hi,

 

ANy update on this?? I have a similar issue where my activity is just waiting for some reason...