Dear Community,
I have an issue where the Worfklow (Flexi-Tas) is sending reminders to the user, after the task has been completed.
As a concrete example:
The Flexi-Task is configureted with a 10-Day reminder Cyclus.
The system generates a new Task on 20.03.2019 and the user completes his Flexi-Task straight away (also 20.03.2019). As the Flexi-Tas was the last task of the Worfklow, also the WF is completed.
Nevertheless, the system sends out the reminder on 30.03.2019 to complete the Flexi-Task (that has already been completed 10 Days before).
Any ideas how to fix this? I cannot identify any issues, and find it extremely weird that a "Completed" Workflow is still able to send out reminders.