Escalation based on date entered in form

  • January 3, 2008
  • 4 replies
  • 9 views

Forum|alt.badge.img+6
I am trying to get an escalation to kick off after an activity has exceeded its "expected duration" but the duration is different for each process instance.  I was going to store the escalation date in a Process Data Field but it appears the Escalate On type will not take a variable.  Anyone know how I can arrange this?

4 replies

Forum|alt.badge.img+9
  • Nintex Partner
  • January 3, 2008

Have you selected the 'Dynamic' option (see attached screenshot)?  You should be able to select Process/Activity data fields as the basis for the escalation


11207i0631EE965E247666.jpg

Forum|alt.badge.img+6
  • Author
  • January 3, 2008
is this a new field in SP1?  I only see "On Specific Date"

Forum|alt.badge.img+9
  • Nintex Partner
  • January 3, 2008

I'm not sure, unfortunately I don't recall how it looked pre-SP1.  This screen shot was definately from an SP1 environment.


Forum|alt.badge.img+6
  • Author
  • January 4, 2008
Thats alright.  I ended up upgrading the system to SP1 yesterday and I now see the correct field above to set the date.  Thanks for the help