How to enable Task Delegation on Nintex 2013

We are having build on one of our client, but found that the Task Delegation option is disappeared from user menu, we would like to know what setting need to be configured in order to activate it. Please advise. delegation‌

Remark:

  • We have already enable all feature on Site Collection / Site Level.
  • We have activate the Nintex feature on all site collection.
  • We are not using System Account.
Reply
2 Replies
eiben
Design Canvas Artiste

Re: How to enable Task Delegation on Nintex 2013

Hi,

you are talking about this menu?

You have to enable long-term-delegation the Central Administration>Nintex Workflow Management>Global Settings

0 Kudos
Reply
Not applicable

Re: How to enable Task Delegation on Nintex 2013

Thank you for your reply Eiben, We get used to mange it by redeploying the solution - Nintexworkflow2013.wsp, we have already deployed the solution and developing workflow on Nintex UI / Forms and related webpart, but have no clue why the menu option is not activated along with the package in the first place, but the redeploy fix it. I think it is a rare case but as a reference, perhaps it can save someone a day. 

0 Kudos
Reply