Task reminders in for Nintex in SharePoint 2010

I need an approver to receive email notifications a day before a deadline date once and the day of the deadline date every hour until they respond. I can't use Task reminders because we are getting ready to migrate to SharePoint Online in a few months. I tried to run parallel actions, but if the Flexi task is completed, I want the workflow to complete. Right now it's just sitting in the Pause until deadline date.

What am I missing?

0 Kudos
Reply
1 Reply
Workflow Hero

Re: Task reminders in for Nintex in SharePoint 2010

You should be able to achieve this with a site workflow scheduled to run daily (where due date is tomorrow) and hourly (where due date is today).

i have a blog post example - let me know if you need additional help after reading it.

Accept as Solution Reply