I’m looking for some guidance on kicking off a start event for the second Tuesday of each month. Any thoughts on how this can be accomplished?
Solved
Schedule Task for the 2nd Tuesday of each month

Best answer by Garrett
Hi
This will require some creativity.
Here is one method
- Schedule to run Weekly → on every Tuesday
- When triggered on Tuesday, check whether the Date is within 8-14 of the Month
IF Yes → continue with the rest of the action
IF No → Exit, Quit or Sleep
Logic Explanation:
- If 1st day of the month is on Tue, then second Tue should be on the 8th
- If 7th day of the month is on Tue, then second Tue should be on the 14th.
- Second Tuesday of the month should fall between 8th and 14th of the month