Hi, I have 100+ processes that need to move from our process manager to another.  Can this be done in bulk? and if so how?  - they would need the actual process and procedure, not a minimode.

Thanks

Best answer by Garciiav

Hello!

Processes could be exported and reimported into a site however exporting groups might be more convenient for large amounts.

 

Export Process

https://help.nintex.com/en-US/promapp/Processes/PrintProcess.htm

 

Here is our Documentation with the steps and more things to keep in mind for exporting Groups:

https://help.nintex.com/en-US/promapp/ProcessGroups/ImportExportProcessGroups.htm

View original
Did this topic help you find an answer to your question?

1 reply

Garciiav
Nintex Employee
Forum|alt.badge.img+3
  • Nintex Employee
  • 3 replies
  • Answer
  • July 1, 2024

Hello!

Processes could be exported and reimported into a site however exporting groups might be more convenient for large amounts.

 

Export Process

https://help.nintex.com/en-US/promapp/Processes/PrintProcess.htm

 

Here is our Documentation with the steps and more things to keep in mind for exporting Groups:

https://help.nintex.com/en-US/promapp/ProcessGroups/ImportExportProcessGroups.htm