Does the 'Activity Instance Overdue' column on the Worklist control take into account working hours?
I have an activity with the expected duration set. Working hours is 8-5 m-f ( so 9 hour work day), so the expected duration is set to 9 hours. The worklist activity has a start date of 12:44pm yesterday and it was 10:14 am when I checked the workflow and it shows overdue. It doesnt seem to take into account working hours.
Are there any other views / reports / controls that display Activity Instance Overdue which does take into account working hours?