I have a requirement for an activity which polls a smart object value every 12 hours, and will workflow will not continue until this proporty is a particular value.   Esclations need to take place if it is taking too long.

 

What is considered best practise for something like this in k2?

1 reply

Forum|alt.badge.img+6
  • August 2, 2017

HI 


 


Please see below links on how to set up escalation, looking at your requirements you can set up the escalation to escalate after 12 hours:


 


http://help.k2.com/onlinehelp/k2appit/userguide/1.5_update5/default.htm#escalation.htm.


 


I hope this gives you an idea of what you would like to achieve on your request.


 


Regards