How to set due date when creating a task.

  • Feb 17, 2011 4:34 PM UTC
  • 1 reply
  • 8 views
  • Translate All

Forum|alt.badge.img

Hi,


I don't see any option in the user task wizard to set due date for the task. Task gets created but it shows up with the blank due date which is unacceptable - if the user see task assigned to him, he has to know when it is due. Am I missing something? Thank you. 

1 reply

Forum|alt.badge.img
  • Aug 29, 2019 7:06 AM UTC

Activity Wizard has a screen "General Properties" where you can see the option at the end which says Expected Duration.

This sets the due date of the task under that activity counting the mentioned days from the start date of the activity.