Solved

How to task list update Assigned due date with the new Adjusted due date.

  • 14 June 2021
  • 1 reply
  • 3 views

Badge +3

I have a task list / on the form and in the list I have  Assigned due date and Adjusted due date. I need the assigned due date to update with the  adjusted due date when the adjusted date date is not empty. 

so.....

Assigned due date == Adjusted due date IF  Adjusted due date is not blank

Any help would be great 

I have research the internet for days with no luck. 

Rule in list or on form or even a workflow............

Thank you

icon

Best answer by pjbro1965 14 June 2021, 20:23

View original

1 reply

Badge +3

So I finally solved this….


 First I added a blank Date field to my list.



Next in my workflow I added update item to my workflow



The workflow runs on modify and is as follows



I hope this helps someone. It took me three days to come up with this. 