Issue Description
When you disable a schedule via the schedules list, the schedule does not stop. Additionally, when you enable a schedule that was disabled via the Edit window, it does not enable the schedule and results in the schedule not working as expected.
Resolution
The fix is available in:
- K2 Five (5.6) Fix Pack 13.
- Ensure you have the correct K2 version and/or Cumulative update installed. See KB001893 to see what Fix Pack level you have installed.
- Download the latest Fix Pack using the links in the table above for the version you require.
- Install the Fix Pack to apply the fix.