AnsweredAssumed Answered

Are there any known issues with Nintex Holidays?

Question asked by nderiley on Jan 5, 2015
Latest reply on Feb 14, 2017 by andrewg@intellinet.com

Hello All!

We had some interesting behavior with one of our workflows regarding holidays.  Our business case is that users are to have 10 business days to complete a task, else the task is terminated.  We had holidays assigned to 12/25, 12/26 and 1/1.  One of our workflows was kicked off such that the 'due date' should have calculated to 1/5 and instead it calculated to 1/2.  I am wondering if having two holidays in a row caused an issue?

 

Thanks,

Erin

Outcomes