Question asked by pkellner on Apr 19, 2016
Latest reply on Oct 27, 2016 by espradli@quiktrip.com

We have a flexi task that is assigned to multiple people.  We want it to escalate to someone for each original assignee.  It is only escalating to the first person, and the other people receive an email stating that their response in no longer required.  Is this the expected behavior for an escalation in a flexi task?  How can we create multiple escalations when there is more than 1 person assigned?  Thanks!