Hi All,

 

I try to build a WF for SP 2010  where a data request is going out every Friday to users to fill in a time sheet on the "active" tasks they were working on in the week.

In nutshell the WF should run for tasks where Area field equals "PMO" and status field not equals "completed" or "cancelled" and its Friday (midday).

I only miss the last part to pause until its "Friday" than wait until the next "Friday".

 

I thought its easy to configure, but now I am stuck with building my WF because of this, hope somebody can help...