Nintex Promapp - Cannot save an activity due date in a Checklist

Issue

Cannot save an activity due date in the Checklists

Resolution

Check the Checklist due date and change it to a later date > this will then allow you to set the activity due dates with a later date (as long as the date is within the Checklist date of completion).

 

TinyTake04-10-2021-01-32-56.png

Additional Information

If you have tried the above and you are still unable to set an activity due date, please contact Promapp Support.

Help > Contact Support

Related Links