I'm using Sharepoint and InfoPath with K2.
After the workflow process is completed the infopath form gets saved to a document library and the item no longer appears in the SP K2 Task List- This I have working so far
At this point when the workflow has been completed is there a way for users to send the infopath form back into the workflow?

Can I send a form to another K2 Task List called completed?

Can you filter the K2 Task list using a not equal to value?

1 reply

Badge +9
Hi,

The K2.net SPS Tasklist works the same as the standard K2.net Worklist, it will only display current Work Items assigned to the logged in user, if a process is completed no work items can be outstanding, this is expected behavior. One can configure a Document Library with a SPS process to start new workflow processes based on various actions on the document library (Insert, Delete and Check In).