Setting reminders on Flexi Task to Due Date

Jump to solution

I am trying to set the reminder within the Flexi Task to send the day after the due date within the InfoPath form.  I programed to Due Date +1 but this does not seem to work as they start sending almost immediately after the task is set.  Is someone able to let me know what I am doing wrong or if I should be calculating this different.

Labels: (2)
Reply
1 Reply
Automation Master
Automation Master

Re: Setting reminders on Flexi Task to Due Date

Jump to solution

Hi Stephanie Farias,

Time between reminders indicate the number of days and not the date time value.

You should first do date calculation and add 1 day to Due Date and then find the number of days between the task assignment date to the new due date using formula.

fn-Round(fn-DateDiffDays(Current Date, DueDate))

The resulting number should be used in the Flexi Task Reminder. hope this helps.

Note here that the second reminder will also take as much time as the first one. So if your 1st reminder goes out in 15 days (which is Due Date +1), 2nd one will go out in 15 days as well.

View solution in original post