I am currenlty trying to find a way to assign task based the the week of the month.

 

Week 1: User 1

Week 2: User 2

Week 3: User 3

Week 4: User 4

Based on the week i will need to assign the task to proper user.

Labels: (3)
0 Kudos
Reply
1 Reply
Nintex Employee
Nintex Employee

Re: Conditional Task Assignments

Hi,
Create a Calculated column that returns the week number of the year.
This MSDN post gives you the calculation.
https://social.msdn.microsoft.com/Forums/sharepoint/en-US/fdbbcf4d-a63c-4f09-991a-9000bcabb267/share...

In your workflow read this column to get the week number.
Then do a modulo 4 to find out the remainder.
If its 0 assign to user1, if its 1 assign to user 2........ if its 3 assign to user 4.