I would like to be able to schedule a site workflow to run on a specific working day.

 

We have deadlines for items to be worked and this is COB the 3rd working day, which next two months is the 5th, but in June its the 3rd. Is the scheduler smart enough to input this?

 

So far the options don't seem to be able to run this way, looking like I can pick the third calander day, tick the box for non-workday meaning it would run on Monday which is the 2nd working day!

 

Any thoughts/work around?

 

Thanks in advance as always

0 Kudos
Reply
1 Reply
Ntobeko
Nintex Employee
Nintex Employee

Re: Schedule site workflow for specific working day

Hi

You could try creating multiple schedules for the workflow to run on the user specified dates