I have a requirement I don't manage to solve.The RACI is defined at the process level. My customer'ld like to define it at task level.

One way to do it  would be to define subprocesses (with RACI) and then to link them in the designer.

 

 

Is there another simpler way to define RACI at task level?

Labels: (1)
0 Kudos
Reply
2 Replies
Lauren_R
Nintex Newbie

Re: RACI at task level

Not within Promapp that I have found - other than as manual text within the task. The RACI is definitely situated at a process level and then the swimlaned roles indicate those responsible at an Activity level. 

Just as an idea, is it an option to include them at the activity level in the swimlane if they participate in the tasks?

 

Lauren

0 Kudos
Reply
Lauren_R
Nintex Newbie

Re: RACI at task level

As an extra option, I have seen RACI matrices created in separate docs and then linked as images or documents underneath the corresponding task within the process.

This doesn't help in terms of the automated notifications, but I just remembered I have seen another Promapp user do this!

0 Kudos