Solved

Nintex Flexi Task Escalation Feature

  • 6 June 2022
  • 1 reply
  • 90 views

We're using Nintex 2013, and I have a flexi task set up so that reminders are sent every 10 business days, 3 reminders total. On the escalation screen, it says "Time to Escalation" and then has the days/hours/minutes fields. Is the time calculated from the end of the reminders, or from the original task assigned date? The documentation says, "Escalation occurs after all reminders have been sent and the specified "Time to escalation" has elapsed." That's a little ambiguous to me.

Thanks!

icon

Best answer by Frankie 16 June 2022, 20:03

View original

1 reply

Userlevel 1
Badge +7

In your example, escalation would occur after 30 days. I recommend you create a small PoC that has 10 min reminders to make testing a bit easier.