Dear Expert,

 

I have seeking for post on how to custome content for out of office email notification. However, i not able to find related post.

 

Currently, when user A configure out of office to delegate the task to user B. User B will receive K2 standard task notification.

 

Subject: FW: New task

 

Content:

Hi User B,

 

You've been forwarded a Task: Open Task

 

To action your task via e-mail, reply with one of the following words:

You may also reply with on of the standard action words:

 

  • Redirect
  • Delegate
  • Sleep

How can i custome the subject and the contect for this email?

 

Thank you.

icon

Best answer by foo_yk 12 November 2019, 07:47

View original

5 replies

Userlevel 6
Badge +16

Hi,


 


There is an existing feature request to customize content of out of office email template. I would highly recommend up voting it, this will help Product Management team to prioritize it in the future.


https://ideas.k2.com/ideas/APIT-I-317


 

Badge +6

Hi,

 

Thank you for your reply.

 

If need to wait for the feature request, i believe it will take some time.

 

Is there a way to disable the email notification? Mean user still can configure the out of office, but no email notification send.

 

So user B only need to action on the form from the task list.

 

Thank you.

Badge +9

Hi foo_yk


 


See the attached link below:


https://community.k2.com/t5/K2-blackpearl-Articles/Task-notifications-after-quot-out-of-office-configuration-quot/ta-p/78643


 


Regards


Elvis


 


 


 


 


 


 


 


 


 

Badge +7

Hello  @foo_yk 

 

Please it is also important to have a glimpse at this string of conversations:https://community.k2.com/t5/K2-Five/How-do-we-customize-the-Out-Of-Office-e-mail-in-K2-5/td-p/109029

 

All the best

Badge +6

Hi all,

 

Since the email not able to be customize, we decided to disable the out of office email notification.

 

Delegated user have to act on the form from the task worklist.

 

Thank you.